MCQ
Small Hydro Power (SHP) Development Scheme (FY 2026-31) MCQ - Practice Questions with Answers
Solve 5 Small Hydro Power (SHP) Development Scheme (FY 2026-31) questions for RAS/RPSC preparation.
Practice questions
Q1Which one of the following statements about project completion and assistance under the Small Hydro Power (SHP) Development Scheme is incorrect?
Option D reverses the rule. No assistance is considered for a project that is not completed or does not begin commercial operations within 7 years from the start of construction. The ordinary deadline is 4 years, a justified one-year grace may be allowed, and quarterly delay reduces eligible assistance by 4%.
Q2What is the total approved outlay of the Small Hydro Power (SHP) Development Scheme for FY 2026-27 to FY 2030-31?
The approved scheme outlay is ₹2,584.60 crore, including about ₹96 crore of committed liabilities from earlier small-hydro schemes. The nearby figure ₹2,532.60 crore relates only to assistance for 1-25 MW projects, while ₹15,000 crore is expected sectoral investment.
Q3Match List I with List II for the approved outlay components of the Small Hydro Power (SHP) Development Scheme. List I: 1. Assistance to 1-25 MW projects, including processing fee; 2. Preparation of at least 200 Detailed Project Reports; 3. Support to technical institutions; 4. Public awareness, capacity building, international cooperation and project monitoring. List II: P. ₹8 crore; Q. ₹14 crore; R. ₹30 crore; S. ₹2,532.60 crore. Select the correct code.
The component table assigns ₹2,532.60 crore to assistance for 1-25 MW projects, including the processing fee; ₹30 crore to at least 200 Detailed Project Reports; ₹8 crore to technical institutions; and ₹14 crore to public awareness, capacity building, international cooperation and project monitoring. Hence 1-S, 2-R, 3-P and 4-Q is the only complete match.
Q4Consider the following statements about the Small Hydro Power (SHP) Development Scheme: 1. It targets approximately 1,500 MW of new SHP capacity. 2. Solar Energy Corporation of India is the National Programme Implementing Agency. 3. A project whose construction started before 18 March 2026 is ineligible. Which of the statements are correct?
All three statements are explicit in the operational guidelines. The capacity objective is approximately 1,500 MW; Solar Energy Corporation of India serves as the national implementing agency; and eligibility is limited to projects whose construction began after the scheme announcement on 18 March 2026.
Q5What installed-capacity range is covered by the Small Hydro Power (SHP) Development Scheme for FY 2026-27 to FY 2030-31?
The operational guidelines define an eligible small hydro project as one having installed capacity of not less than 1 MW and up to and including 25 MW. Thus, both endpoints matter: a sub-1 MW project and a project exceeding 25 MW fall outside this scheme.
You've seen 5 of 5 sample questions
Unlimited practice on Small Hydro Power (SHP) Development Scheme (FY 2026-31) comes with the RAS Test Series + Practice pack or Gate Pass.
