Aspirant Academy

MCQ

Small Hydro Power (SHP) Development Scheme (FY 2026-31) MCQ - Practice Questions with Answers

Solve 5 Small Hydro Power (SHP) Development Scheme (FY 2026-31) questions for RAS/RPSC preparation.

Practice questions

Q1Which one of the following statements about project completion and assistance under the Small Hydro Power (SHP) Development Scheme is incorrect?

A The normal completion period is 4 years from the start of construction.
B A justified delay may receive a grace period of 1 year.
C Eligible assistance is reduced by 4% for every quarter of delay.
D Assistance remains fully available even if commercial operations do not begin within 7 years.
Explanation

Option D reverses the rule. No assistance is considered for a project that is not completed or does not begin commercial operations within 7 years from the start of construction. The ordinary deadline is 4 years, a justified one-year grace may be allowed, and quarterly delay reduces eligible assistance by 4%.

Q2What is the total approved outlay of the Small Hydro Power (SHP) Development Scheme for FY 2026-27 to FY 2030-31?

A ₹2,532.60 crore
B ₹2,584.60 crore
C ₹15,000 crore
D ₹30 crore
Explanation

The approved scheme outlay is ₹2,584.60 crore, including about ₹96 crore of committed liabilities from earlier small-hydro schemes. The nearby figure ₹2,532.60 crore relates only to assistance for 1-25 MW projects, while ₹15,000 crore is expected sectoral investment.

Q3Match List I with List II for the approved outlay components of the Small Hydro Power (SHP) Development Scheme. List I: 1. Assistance to 1-25 MW projects, including processing fee; 2. Preparation of at least 200 Detailed Project Reports; 3. Support to technical institutions; 4. Public awareness, capacity building, international cooperation and project monitoring. List II: P. ₹8 crore; Q. ₹14 crore; R. ₹30 crore; S. ₹2,532.60 crore. Select the correct code.

A 1-S, 2-R, 3-P, 4-Q
B 1-R, 2-S, 3-Q, 4-P
C 1-S, 2-P, 3-R, 4-Q
D 1-Q, 2-R, 3-P, 4-S
Explanation

The component table assigns ₹2,532.60 crore to assistance for 1-25 MW projects, including the processing fee; ₹30 crore to at least 200 Detailed Project Reports; ₹8 crore to technical institutions; and ₹14 crore to public awareness, capacity building, international cooperation and project monitoring. Hence 1-S, 2-R, 3-P and 4-Q is the only complete match.

Q4Consider the following statements about the Small Hydro Power (SHP) Development Scheme: 1. It targets approximately 1,500 MW of new SHP capacity. 2. Solar Energy Corporation of India is the National Programme Implementing Agency. 3. A project whose construction started before 18 March 2026 is ineligible. Which of the statements are correct?

A 1 only
B 1 and 2 only
C 1, 2 and 3
D 2 and 3 only
Explanation

All three statements are explicit in the operational guidelines. The capacity objective is approximately 1,500 MW; Solar Energy Corporation of India serves as the national implementing agency; and eligibility is limited to projects whose construction began after the scheme announcement on 18 March 2026.

Q5What installed-capacity range is covered by the Small Hydro Power (SHP) Development Scheme for FY 2026-27 to FY 2030-31?

A Not less than 1 MW and up to 25 MW
B Below 1 MW only
C Above 25 MW and up to 100 MW
D Not less than 100 MW and up to 500 MW
Explanation

The operational guidelines define an eligible small hydro project as one having installed capacity of not less than 1 MW and up to and including 25 MW. Thus, both endpoints matter: a sub-1 MW project and a project exceeding 25 MW fall outside this scheme.

You've seen 5 of 5 sample questions

Unlimited practice on Small Hydro Power (SHP) Development Scheme (FY 2026-31) comes with the RAS Test Series + Practice pack or Gate Pass.

More topics in Government Schemes

Explore other subjects