Q1Consider the following statements about the track slab manufacturing facility near Anand: 1. The facility was opened near Anand in Gujarat. 2. It was designed for production of 45,000 precast track slabs for the MAHSR project. 3. Approximately 2,000 track slabs are required per track kilometre. Which of the statements given above are correct?

A 1 and 2 only
B 1 and 3 only
C 2 and 3 only
D 1, 2 and 3
Explanation

Statements 1 and 2 are correct. Statement 3 is false: NHSRCL says approximately 200, not 2,000, track slabs are required per track kilometre.

Q2Consider the following statements: 1. There will be three rolling-stock maintenance depots in the MAHSR corridor. 2. The depots will be located at Surat, Thane and Sabarmati. 3. Surat depot will have facilities for bogie and general overhauling in addition to regular inspections. Which of the statements given above are correct?

A 1 only
B 1 and 2 only
C 2 and 3 only
D 1, 2 and 3
Explanation

Statements 1 and 2 are true. Statement 3 is false because bogie and general overhauling facilities are specified for Sabarmati depot, not Surat depot.

Q31. The J-slab ballastless track system for the MAHSR project has pre-cast track slabs on an RC track bed. 2. The RC track bed for the slab system is about 300 mm thick. 3. Cement asphalt mortar is used between the track slab and the RC track bed. 4. The J-slab system uses loose stone ballast between sleepers and rails. Which of the statements given above are correct?

A 1 and 4 only
B 2 and 3 only
C 1, 2 and 3 only
D 1, 2, 3 and 4
Explanation

Statement 1 is true because the official release describes pre-cast track slabs on an RC track bed. Statement 2 is true because it gives the RC track bed thickness as about 300 mm. Statement 3 is true because CAM is injected between the slab and the RC bed. Statement 4 is false because this is described as ballastless slab track technology, not a loose stone ballast system.

Q4Consider the following statements: 1. The MAHSR corridor will use a J-Slab ballastless track system based on the Japanese Shinkansen track system. 2. NHSRCL lists RC track bed, cement asphalt mortar, pre-cast track slab and rails with fasteners as the four main components of this system. 3. Track installation is described as primarily manual because Japanese construction practices avoid mechanised laying. 4. NHSRCL states that all track construction machines for this system are imported without any technology transfer. Which of the statements given above are correct?

A 1 and 3 only
B 1, 2 and 4 only
C 1, 2 and 3 only
D 1 and 2 only
Explanation

Statement 1 is correct: the J-Slab ballastless system is based on Japanese Shinkansen track. Statement 2 is correct: those four components are listed. Statement 3 is incorrect because the process is described as fully mechanized. Statement 4 is incorrect because NHSRCL says most machines are manufactured in India and one type involves technology transfer from Japan.

Q5Consider the following statements about earthquake-safety arrangements for the Mumbai-Ahmedabad High Speed Rail corridor: 1. Twenty-eight seismometers are planned for the early earthquake detection system. 2. Twenty-two of these seismometers are to be installed along the alignment. 3. The six inland seismometers are to be installed only in Rajasthan. 4. The system is intended to enable automatic power shutdown and emergency braking. Which of the statements given above are correct?

A 1 and 3 only
B 2 and 4 only
C 1, 2 and 4 only
D 1, 2, 3 and 4
Explanation

Statements 1, 2 and 4 are correct: NHSRCL describes 28 seismometers, 22 along the alignment, and automatic power shutdown/emergency braking. Statement 3 is false because the inland seismometers are to be in seismically vulnerable areas of Maharashtra and Gujarat, not Rajasthan.

You've seen 5 of 82 sample questions

Unlimited practice on High-Speed Rail comes with the RAS Test Series + Practice pack or Gate Pass.

More questions

6Consider the following statements: 1. The Mumbai-Ahmedabad High Speed Rail corridor is India's first bullet train project and spans 508 kilometres. 2. The corridor starts from the Bandra Kurla Complex area in Maharashtra and terminates at Sabarmati. 3. With limited stops, the entire journey is expected to take about 3 hours and 7 minutes. Which of the statements given above are correct?

A1 only
B1 and 2 only
C2 and 3 only
D1, 2 and 3

7Consider the following statements about the 2016 feasibility-report information on the Mumbai-Ahmedabad high speed corridor: 1. The joint feasibility study by JICA and the Government of India was completed in July 2015. 2. The feasibility-report information gave 2.07 hours as the journey time for a fast train. 3. The feasibility-report information estimated the completion cost at approximately Rs. 1,08,000 crore. Which of the statements given above are correct?

A1 and 2 only
B1 and 3 only
C2 and 3 only
D1, 2 and 3

8Consider the following statements about station distribution on the Mumbai-Ahmedabad High Speed Rail corridor: 1. The total number of planned stations was listed as 12. 2. The 12 stations were divided as 8 in Gujarat and 4 in Maharashtra. 3. Surat was listed as one of the Maharashtra stations. Which of the statements given above are correct?

A1 and 2 only
B1 and 3 only
C2 and 3 only
DNone of the above

9Consider the following statements about stations, depots and control arrangements on the Mumbai-Ahmedabad High-Speed Rail corridor: 1. Out of 12 stations, 8 are in Gujarat and 4 are in Maharashtra. 2. The operational control centre is at Sabarmati. 3. Gujarat has two depots, at Surat and Sabarmati. 4. Maharashtra has two depots, at Thane and Boisar. Which of the statements given above are correct?

A1 and 3 only
B2 and 4 only
C1, 2 and 3 only
D1, 2, 3 and 4

101. The Mumbai-Ahmedabad High Speed Rail corridor is about 508 km long. 2. The corridor is planned with 20 stations. 3. The corridor will offer fast connectivity between Maharashtra and Gujarat states in western India. 4. The project's maximum operational speed is 160 km/h. Which of the statements given above are correct?

A1 and 3 only
B1, 2 and 3 only
C2 and 4 only
D1, 3 and 4 only

111. The MAHSR corridor salient features list three depots. 2. Gujarat is listed with two depots. 3. The Operational Control Center is listed at Sabarmati. 4. Maharashtra is listed with three depots. Which of the statements given above are correct?

A1 and 2 only
B2 and 4 only
C1 and 3 only
D1, 2 and 3 only

12Consider the following statements about the J-slab track system for the bullet train project: 1. The project will use a J-slab ballastless track system based on the Japanese Shinkansen track system. 2. NHSRCL states that this is the first time the J-slab ballastless track system is being used in India. 3. The Anand factory was designed to produce 600 slabs per day. Which of the statements given above are correct?

A1 and 2 only
B1 and 3 only
C2 and 3 only
DNone of the above

13Consider the following statements about the track system used for the MAHSR corridor: 1. The J-slab ballastless track system is being used in India for the first time on this corridor. 2. The RC track bed has a thickness of approximately 300 mm. 3. The RC anchors are stated as 520 mm in diameter and 260 mm in height. Which of the statements given above are correct?

A1 and 2 only
B1 and 3 only
C2 and 3 only
D1, 2 and 3

141. The Mumbai-Ahmedabad High Speed Rail corridor has a listed length of 508.17 km. 2. Its maximum operational speed is listed as 320 km/h. 3. The all-stops journey time is listed as 2.58 hours. 4. The limited-stops journey time is listed as 3.50 hours. Which of the statements given above are correct?

A1 and 4 only
B2 and 3 only
C1 and 2 only
D1, 2 and 3 only

15Consider the following statements about weather-monitoring systems on the Mumbai-Ahmedabad High Speed Rail corridor: 1. Six instrumented rain gauge stations are planned. 2. Anemometers are proposed at 14 locations. 3. The cited wind-speed measurement range of the anemometers is 0-180 kmph. 4. Train operation control is linked to wind-speed bands such as 72 kmph to 130 kmph. Which of the statements given above are correct?

A1 and 3 only
B2 and 3 only
C1, 2 and 3 only
D1, 2 and 4 only