Q1. What did the Atomic Energy Regulatory Board permit for Kudankulam Units 5 and 6 as reported on 1 May 2026?
Explanation
AERB permitted Major Equipment Erection at Kudankulam Units 5 and 6 after reviewing design and civil construction progress. The release did not announce commercial operation, closure of existing units or transfer of project ownership.