Q1. Consider the following statements about policy measures for ESS in India: 1. Complete waiver of ISTS charges was made applicable to BESS and PSP projects commissioned up to 30 June 2025, subject to conditions. 2. The transmission charges after 30 June 2025 were to be increased by 25% every month until 2028. 3. Consumer rules asked users of diesel generator sets as essential backup to endeavour to shift to cleaner technology such as renewable energy with battery storage. 4. The Ministry of Power's March 2022 BESS procurement guidelines excluded ancillary services. Which of the statements given above are correct?
Explanation
Statements 1 and 3 are correct. Statement 2 is false because the increase is annual, not monthly. Statement 4 is false because the guidelines include ancillary services.