Thermal Power Modernisation MCQ - Practice Questions with Answers
Solve 2 Thermal Power Modernisation questions for RAS/RPSC preparation.
Practice questions
Q1With reference to the CEA's plan for ageing thermal-power units, consider the following statements: 1. The identified units were more than 20 years old as of December 2022. 2. The phased schedule covers 223 units with a total capacity of 63,440 MW. Which of the statements given above is/are correct?
Both statements are correct. The CEA identified 223 units that were more than 20 years old as of December 2022. The schedule covers all 223 units, with a combined capacity of 63,440 MW, in nine phases.
Q2Consider the following statements about financing and implementation of the thermal-power modernisation plan: 1. The Union government currently provides dedicated funds for the work. 2. All identified units are to be modernised in a single phase. Which of the statements given above is/are correct?
Neither statement is correct. The Union government currently provides neither funds nor a central-sector scheme for this work. After assessing feasibility, the generating company is expected to arrange commercial financing. The work is planned across nine phases, not one.