Q1Consider the following statements regarding the newly approved third line project: 1. The third line is being constructed on the Northern Railway zone. 2. The existing section is running at 95% capacity utilisation. Which of the statements given above is/are correct?

A 1 only
B 2 only
C Both 1 and 2
D Neither 1 nor 2
Explanation

Both statements are incorrect. The third line is being constructed on the South Eastern Railway (not the Northern Railway), between Nimpura West Outer Cabin and Midnapur. The existing section is running at 115.71% capacity utilisation, not 95%, indicating severe congestion.