Union Minister of Electronics and Information Technology Ashwini Vaishnaw on April 19, 2026 laid the foundation stone for India's first advanced 3D semiconductor packaging facility at Info Valley in Khordha district near Bhubaneswar, Odisha. The greenfield, vertically integrated advanced packaging and embedded glass substrate ATMP (Assembly, Testing, Marking and Packaging) plant is being set up by Heterogeneous Integration Packaging Solutions Pvt Ltd (HIPSPL), the wholly owned Indian subsidiary of US-based 3D Glass Solutions Inc. (3DGS). The total project cost is ₹1,943.53 crore, which includes approved Central fiscal support of ₹799 crore under the India Semiconductor Mission and additional Odisha state support of approximately ₹399.5 crore. The facility will produce 70,000 advanced glass panels annually, around 50 million assembled units and roughly 13,000 advanced 3D Heterogeneous Integration (3DHI) modules every year. It will cater to high-growth sectors such as data centres, Artificial Intelligence and Machine Learning, 5G/6G communications, automotive radar, defence electronics, aerospace applications and photonics. Commercial production is targeted to begin by August 2028, with full-scale output by August 2030. The project is expected to generate around 1,500 direct jobs and a much larger ecosystem of indirect employment in skilled manufacturing. Odisha Chief Minister Mohan Charan Majhi attended the ceremony and said the unit positions the state as a hub of next-generation chip packaging, complementing India's ongoing fabrication efforts at Dholera, Gujarat and Sanand.
Union Minister Ashwini Vaishnaw Lays Foundation of India's First Advanced 3D Semiconductor Packaging Unit at Info Valley, Bhubaneswar on April 19, 2026; ₹1,943.53 Crore HIPSPL Project to Serve AI, 5G/6G, Defence Electronics
Union Minister Ashwini Vaishnaw on April 19, 2026 laid the foundation stone for India's first advanced 3D semiconductor packaging facility at Info Valley, Bhubaneswar, Odisha. The ₹1,943.53 crore HIPSPL plant by 3D Glass Solutions Inc. will produce 70,000 glass panels and 13,000 3DHI modules a year for AI, 5G/6G, defence and aerospace, with commercial output by August 2028.
Key facts
- Foundation stone laid by Union Electronics & IT Minister Ashwini Vaishnaw on April 19, 2026 at Info Valley, Khordha district, near Bhubaneswar, Odisha.
- Project executed by Heterogeneous Integration Packaging Solutions Pvt Ltd (HIPSPL), wholly owned Indian subsidiary of 3D Glass Solutions Inc. (3DGS), USA.
- Total cost ₹1,943.53 crore, including ₹799 crore Central fiscal support under the India Semiconductor Mission and ~₹399.5 crore Odisha state support.
- Annual capacity: 70,000 advanced glass panels, ~50 million assembled units, ~13,000 advanced 3D Heterogeneous Integration (3DHI) modules.
- Target sectors: data centres, AI/ML, 5G/6G communications, automotive radar, defence electronics, aerospace and photonics.
- Commercial production targeted by August 2028 and full-scale output by August 2030; about 1,500 direct jobs expected.
- Complements India's ongoing fab efforts at Dholera (Gujarat) and Sanand, expanding the country's end-to-end semiconductor stack into advanced packaging.
6-axis classification
Appears in these topics
Practice MCQ from this story
SolveTap an option below. Correct or incorrect feedback appears instantly.
With reference to India's first advanced 3D semiconductor packaging unit whose foundation stone was laid on 19 April 2026, consider the following statements:\n1. The plant is being set up at Info Valley in Khordha district of Odisha by a wholly owned Indian subsidiary of US-based 3D Glass Solutions Inc.\n2. The total project cost is ₹1,943.53 crore, including approved Central fiscal support of ₹799 crore under the India Semiconductor Mission.\n3. Commercial production is targeted to begin by August 2030, with full-scale output by August 2035.\nWhich of the statements given above are correct?
Statements 1 and 2 are correct. The HIPSPL plant — set up by the Indian subsidiary of US-based 3D Glass Solutions Inc. at Info Valley, Khordha district, Odisha — has a total project cost of ₹1,943.53 crore, of which ₹799 crore is Central support under the India Semiconductor Mission. Statement 3 is incorrect: commercial production is targeted by August 2028 (not 2030), and full-scale output by August 2030 (not 2035).
Source: Press Information Bureau
Frequently asked questions
Where is India's first advanced 3D semiconductor packaging unit being set up?
At Info Valley in Khordha district near Bhubaneswar, Odisha; foundation stone laid on April 19, 2026 by Union Minister Ashwini Vaishnaw.
Which company is implementing the project and what is the total investment?
Heterogeneous Integration Packaging Solutions Pvt Ltd (HIPSPL), the wholly owned Indian subsidiary of US-based 3D Glass Solutions Inc., is implementing the ₹1,943.53 crore project.
How much fiscal support has the Centre approved?
₹799 crore under the India Semiconductor Mission, in addition to about ₹399.5 crore of state support from Odisha.
What will the unit produce annually and for which sectors?
70,000 glass panels, about 50 million assembled units and roughly 13,000 3DHI modules each year for AI, 5G/6G, automotive radar, defence electronics, aerospace and photonics.
When will commercial production begin?
Commercial production is targeted by August 2028, with full-scale output by August 2030.